Installation Levels

        Level I
        This is the installation or replacement of the same or similar, existing pieces of
        foodservice equipment in an existing foodservice establishment.



        Level II
        This is the installation of new equipment for entire kitchens during remodel
        or  construction  phase,  to  include  receiving,  warehousing,  consolidation  of
        equipment and delivery for each phase of installation, assembly, set in place,
        leveled, caulked and trimmed as needed, with final corrections made, started
        up and tested.



        Level III
        This includes all of Levels I and II and may or may not include all or some other
        options (such as hoods, HVAC, fire suppression, complete electrical or plumbing
        contracting, carpentry, communications, computers, flooring, roofing, stainless
        steel welding or complete general contracting as well as pulling all necessary
        permits).